Tentative Programme
20/12/2013 11:58
PROGRAMME OF NATIONAL TECHNICAL SEMINAR OF IPWE (INDIA) On Management of P.Way Works Through Need Based Outsourcing & Design Construction and Maintenance of Railway Tunnels |
||||
Dated: 23rd and 24th January-2014 | ||||
Venue: B.M. Birla Auditorium Statue Circle, C-Scheme-Jaipur | ||||
Date: 23rd January 2014 | ||||
Registration of Delegates | 8.30 | |||
Inauguration of Technical Exhibition | 9.30 | |||
Inauguration of Technical Seminar | 10.00-11.20 | |||
Tea | 11.20-11.50 | |||
Technical Session I "Management of P.Way Works Through Need Based Outsourcing" | 11.50-13.30 | |||
Topic | Author | Rly | ||
i | Outsourcing of Ultrasonic Testing of Rails/ Welds: Issues and challenges | Satish Kumar Pandey ED/Track & A.K.Sharma ADE/Track |
RDSO | |
ii | Thoughts For Better ‘Dasha’ And ‘Disha’ Of Track Maintenance Cadre On Indian Railways | Alok Kumar EDCE/G | Railway Board | |
iii | Attracting Private investment in Setting up of Track Machine Overhauling (POH) facility –concept and financial modeling for a successful venture | Vivek Kumar Gupta , CE( TM) | WR | |
iv | Permanent way works- outsourcing should improve quality and increase productivity | J S Mundrey | Ret | |
Lunch | 13.30-14.30 | |||
Technical Session II "Management of P.Way Works Through Need Based Outsourcing" | 14.30-16.00 | |||
Topic | Author | Rly | ||
i | Options and Trends- Outsourcing of Maintenance of Permanent way | Neeraj Agrawal GM/Civil |
DFCCIL | |
ii | Track Maintenance Through Outsourcing - Shortcomings and Suggestions | Mangal Bihari Vijay CTE & Manoj Gupta DyCE/Track |
NWR | |
iii | Management of P.Way Works through need based outsourcing | Pankaj Kunwar, Sr.DEN(Co)/Ranchi R.K. Verma, SSE(P.Way)/Bano |
SER | |
iv | COMPLETE OUTSOURCING OF TRACK MAINTENANCE IN FREIGHT SECTIONS: | A K Patel, SrDEN/Coordination/CKP Rahul Singh, AEN/West/CKP | SER | |
Tea | 16.00-16.20 | |||
Annual General Body Meeting and visit to Technical Exhibition | 16.20-17.00 | |||
Cultural Programme followed by Dinner | 19.00 | |||
Date: 24th January 2014 | ||||
Technical Session III "Design Construction & Maintenance of Tunnels" | 9.30-11.00 | |||
Topic | Author | Rly | ||
i | DESIGN ASPECTS FOR TUNNEL CONSTRUCTION | Satish Kumar, IRSE, PCE & Kamal Dev Ralh, IRSE CE/C |
NCR | |
ii | Managing Surprises in Tunnel Projects | Vipul Kumar ED/Track II | RDSO | |
iii | Construction of Tunnel No. 7 From Face-2(Silchar end) In Extremely Soft Ground Conditions Under Lumding-Silchar Gauge Conversion Project of N.F.Railway | A.S Garud CAO/Con 1, Ajit Pandit CE/Con 1 & Ajay Pradhan Dy CE/Con 2 |
NFR | |
iv | Tunneling using conventional Drill Blast method: A case study of Karjat tunnel | SK Garg SPW | IRICEN | |
Tea | 11.00-11.30 | |||
Technical Session III "Design Construction & Maintenance of Tunnels" | 11.30-13.00 | |||
Topic | Author | Rly | ||
i | Global Experience of design, Construction & maintenance of Railway Tunnels with special reference to Indian Railways | M.M. Agarwal Former CE/NR & ED IPWE & K.K.Miglani DyCE/Track |
NR | |
ii | Tunnel Inspection and Maintenance – A Practical Approach : Key provisions of RDSO Guidelines GE: G-0015 | Brijesh Kumar, ED/ GE Sanjay Mishra, Director/GE | RDSO | |
iii | Tunnel Ventilation & Fire Safety in PIR-PANJAL Tunnel T-80 of USBRL Project | Hitesh Khanna, Director/Woks, | Ircon International Ltd | |
iv | Design, Construction & Maintenance of Railway Tunnels | J.N. Laldas CRE | ECoR | |
Lunch | 13.00-14.00 | |||
Session V (Presentation by Trade & Industry) | 14.00-15.00 | |||
Technical Session VI "Miscellaneous Paper by Members" | 15.00-16.00 | |||
Topic | Author | Rly | ||
i | Effect of Flat Tyre on 90 UTS Rail - A case study in the Amguri-Safrai Section of Tinsukia Division | B. Ashok, CTE/NFR & R. K. Das, Dy. CE/TD/NFR |
NFR | |
ii | Green Building: A case study of New IRICEN Administrative Building | NC Sharda SPT1/IRICEN, Suresh Pakhare DyCE/C/Pune/CR, Gautam Kumar XEN/C/Pune/CR |
IRICEN, CR | |
iii | Construction of Road Under Bridge by Cut & Cover method - A case study on Bikaner division of NWR | N. K. Sharma, sr. DEN/Co/BKN & Vishal Gupta, Sr. DEN/North/BKN | NWR | |
iv | RUB by Cut & Cover Method using Relieving Girder | Pankaj Soin Sr DEN/West/Ajmer | NWR | |
Tea | 16.00-16.30 | |||
Valedictory Session | 16.30-17.00 |